Case Study

Noise and Vibration Monitored and Managed During Erskine Bridge Project

Infrastructure
Civil Engineering
Erskine Bridge
Project Overview

The village of Old Kilpatrick in West Dunbartonshire in Scotland sits under the Erskine Bridge on the banks of the River Clyde on the outskirts of Glasgow. Completed in 1971, the bridge is a steel, cable-stayed bridge used by all types of motor vehicles, cyclists and pedestrians. As well as crossing the Clyde, the bridge also crosses the Forth and Clyde Canal and the North Clyde railway line. A small part of Kilpatrick railway station is situated underneath the bridge at the north side. The bridge forms part of the A898 road and is set at a high level to allow the passage of shipping beneath.

The Glasgow Circular high-pressure gas main currently crosses the River Clyde suspended from the Erskine Bridge at Old Kirkpatrick. In a major project, the current pipeline is being replaced and diverted to an alternative crossing. Complex drilling and tunnelling techniques, including Horizontal Directional Drilling (HDD) and micro tunnelling, are being used to overcome challenges to install 1.9km of new pipeline beneath the river.

Ground conditions mean that the solution is not straightforward, with steep angles for the pipeline route dictated by the river bank geometry and existing buildings and structures. In addition to crossing beneath the river, the new pipeline will also pass beneath a canal, a railway and the carriageway of the A82.

The project, being undertaken by J Murphy and sons, is expected to be completed by the end of 2019.

Challenge

The project that J Murphy and Sons was contracted to undertake was complex. The location of the new high-density, high-pressure gas pipeline being constructed and its route across a river, canal, major ‘A’ road, water main, and live railway tracks, as well as the rocky ground conditions and steep angles of the river bank, all combined to make conditions and logistics extremely challenging.

A wide range of high power, high precision Horizontal Directional Drilling, Auger Boring and Micro Tunnelling techniques were required to replace the existing pipeline with the new 1.9km 39 bar pipeline. Open-cut installation of the pipeline was also undertaken, involving trench excavation using noisy plant.

The fact that the works were taking place in close proximity to schools, churches, local businesses and residential properties, also meant that the potential for noise pollution from these varied and intensive construction tasks was high.

As a result of all these factors, it was essential to monitor noise and vibration levels to ensure that sensitive areas of the environment were not disturbed and that concerns from local residents were alleviated.

Solution

RVT came to assess the situation, and subsequently recommended the installation of two Monitex Vibration Monitors, and a total of six Monitex Noise Monitors to be positioned around the most critical parts of the site. These state-of-the-art monitors provided the contractors with an accurate and continuous picture of the amount of noise and vibration being produced.

These innovative systems are designed for maximum ease-of-use, even in harsh outdoor conditions. The real-time readings they provided allowed site management to constantly assess the situation, and ensure that workers, the public and the local environment, were not impacted by the major works taking place throughout the project.

"We were very happy with the product and service” - SHESQ Advisor, Murphy